SSE Generation engaged Hochtief Solutions under an NEC2 Engineering and Construction Contract to design and construct a hydroelectric scheme at Glendoe, Scotland. The works included a 6.2km headrace tunnel (HRT) running from a reservoir, through the Conagleann Fault Zone (CFZ), to a turbine.
The central legal issues were:
- Whether the tunnel collapse constituted a “Defect” under clause 11.2(15)
- Whether Hochtief’s liability was limited by Option M, which required only the exercise of reasonable skill and care in design
- Whether the collapse was caused by a defect existing at take over, which would classify it as a contractor’s risk under clause 80.1
- Whether joint names insurance precluded SSE’s claim
- Whether Hochtief was obligated to correct the damage under clauses 43.1, 46.4, and 82.1
The Inner House found that the collapse was due to inadequate support measures in the CFZ, particularly the failure to apply shotcrete to erodible rock, which was necessary to meet the 75-year design life requirement. The failure was classed as both a breach of the Works Information and the accepted design, thus constituting a “Defect” under the contract. The court held that the issue was not with the design itself but with the implementation of the design. Since Option M only applied to design defects and not implementation failures, it did not shield Hochtief from liability.
This case carries substantial implications for those engaged under NEC contracts. The judgment clarifies that:
- Contractors remain fully liable for implementation failures, even where a limitation clause such as Option M exists. Such clauses are limited to design faults only.
- The obligation to meet a specified design life is not merely aspirational; it is an enforceable element of the Works Information. If the works do not meet this requirement, they are defective.
- Contractual obligations to correct defects or repair damage persist and cannot be avoided by reference to insurance arrangements unless clearly stated in the contract.
- The court recognised a distinction between the contractor’s obligation to design with reasonable skill and care and the broader duty to construct the works in accordance with the contract. The latter remains subject to a higher standard of fitness for purpose.